M1-M16 | Platform R&D and Integration
Motor module, ESC variants, casting interfaces, and reducer development with bench validation.
36-Month Delivery Path from TRL 5 to TRL 7
The implementation model combines R&D validation, pilot deployment, and industrialization preparation to generate both technical evidence and replication readiness for follow-on scale-up.
Programme Timeline
M12-M30 | Pilot Demonstrations
Site deployment in Norway and Bulgaria with baseline and operational performance measurement.
M24-M36 | Industrialization Preparation
Pre-compliance, supply-chain planning, and commercial transition roadmap for post-LIFE scale.
Milestone-Oriented Governance
Key Milestones
- M5: single module validation complete.
- M12: integrated stack-housing-reducer lab validation.
- M16: pilot units installed, TRL transition phase active.
- M34-M36: final validation and next-phase roadmap completion.
Risk-Control Logic
- Thermal and dynamic stacking risks managed through simulation and test loops.
- Reducer durability risk managed through material and life-cycle validation.
- Deployment timing risk mitigated with phased pilot scheduling and buffer logic.